Altaley Mining Closes Non-Brokered Private Placement and Reports on Q1 2022 Financials

Altaley Mining Corporation (TSXV: ATLY) (OTCQX: ATLYF) (FSE: TSGA) (the “Company” or “Altaley“) is pleased to announce that it has closed the final tranche (the “Final Tranche”) of its non-brokered private placement previously announced on March 17, 2022 and has released its Q1 2022 financial results.

Private Placement

The Company has closed a Final Tranche and issued 2,169,418 units (each, a “Unit“) at a price of $0.35 per Unit for gross proceeds of $759,296.30. In total, the Company issued 14,285,714 Units at a price of $0.35 per Unit for aggregate gross proceeds of $5,000,000. Each Unit consists of one common share (a “Common Share“) and one-half of one common share purchase warrant (each whole such warrant, a “Warrant“). Each Warrant will entitle the holder to purchase one additional Common Share of the Company at a price of $0.55 per Common Share within 24 months from the relevant closing date (the “Closing Date“), subject to an acceleration clause. If, at any time between the Closing Date and the expiry date, the closing price of the Company’s common shares on the TSX Venture Exchange (the ”Exchange”) exceeds $0.75 for 15 consecutive trading days, then the Company will earn the right, by providing notice to the warrant holder via news release or written notice, to accelerate the expiry date of the warrants to 4 p.m. (Vancouver time) on that date which is 30 days from the date of the acceleration notice. See April 21, 2022, news release regarding first tranche closing. All securities issued under the Private Placement are subject to a hold period expiring four months and one day after the Closing Date. Total issued and outstanding Common Shares of the Company after completion of the Private Placement is 277,894,422.

In accordance with applicable securities laws and the policies of the Exchange, the Company will issue 42,000 Units of the Company as a finder’s fee to certain finders in connection with the Final Tranche.

A portion of the Final Tranche closing was purchased by an affiliate of a director of the Company. Accordingly, this participation in the Private Placement is considered a related-party transaction as such term is defined under Multilateral Instrument 61-101 (Protection of Minority Security Holders in Special Transactions). The Company is relying on exemptions from the formal valuation and minority shareholder approval requirements provided under MI 61-101 (sections 5.5(b) and 5.7(1)(b) of MI 61-101) on the basis that the Company is listed on the Exchange (and has no shares listed on the Toronto Stock Exchange or certain other named exchanges) and the fair market value of the securities distributed to the related party under the Private Placement was less than $2,500,000. The Private Placement was approved by the board of directors of the Company, which includes at least one independent director who is not an employee of the Company, which considered the best interests of the Company in completing the Private Placement. The Company did not file a material change report more than 21 days before the expected closing of the insider transactions as the details of the Private Placement and the participation therein by related parties of the Company were not settled until shortly prior to closing and the Company wished to close on an expedited basis for sound business reasons and in a time frame consistent with usual market practices for transactions of this nature.

The net proceeds from the Units will be used by the Company for working capital purposes related to the ramp-up of mining and milling operations at the Tahuehueto Mine and for general working capital purposes.

The private placement financing is subject to final Exchange approval

Q1 2022 Financials

During the three months ended March 31, 2022, Campo Morado produced 9,657 tonnes of zinc concentrate grading an average of 46% zinc, 1.58 g/t gold, 609 g/t silver and sold approximately 9,781 tonnes of zinc concentrate generating Q1-2022 revenue from zinc concentrate of US$12.34 million. Additionally, produced 2,379 tonnes of lead concentrate grading an average of 19% lead, 2.37% copper, 4.66 g/t gold, 647 g/t silver and sold 2,626 tonnes generating Q1-2022 revenue from lead concentrate of US$1.84 million.

Approximately 176,610 tonnes of mineralized material were mined with average grades of 3.59% zinc, 0.91% lead, 103 g/t silver, 0.83 g/t gold achieving recoveries of 70.1% in zinc, 27.7% in lead, 9.8% in gold, and 27.6% in silver.

An estimated 176,610 tonnes of mineralized material were processed through the processing plant at a C1 cash cost per lb of US$1.26.

Ralph Shearing states, “Q1 2022 was a difficult quarter at Campo Morado where mechanical issues resulting in excessive mill downtime combined with lower recoveries, lower mill feed head grade mineralized material plus increased off taker charges all combined to substantially reduce operating profit and increase costs during the quarter. The mechanical issues have been resolved and the mine plan is producing increased grade mill feed with recoveries of zinc back on track. In addition, the mine started copper concentrate production during mid-May which we are expecting will add an additional revenue source to the project. We anticipate a much improved second quarter.”

The following table and subsequent discussion provide a summary of the operating performance of the Company for the three months ended March 31, 2022, and 2021.

Table 1

Campo Morado Mine

Production and concentrate sales in Q1-2022 were negatively affected compared to all quarters of 2021 as a result of the following;

  • lost production days largely related to mechanical issues with the SAG mill reduction gear box and scheduled maintenance, where a combined 11 days of operation were lost during the quarter,
  • maintenance costs for both plants increased as a result of the above mechanical issue.
  • average head grades and recoveries were lower by the following amounts:
    • Gold Head Grade from 1.07 g/T 2021 to 0.82 g/t 2022
    • Silver Head Grade from 124.7 g/t 2021 to 102.2 g/t 2022 
    • Au recoveries from 13% in Zn con and 8% in Pb con to 10% and 6% respectively
    • Ag recoveries from 35% in Zn con and 9% in Pb con to 30% and 7% respectively
    • Pb recoveries from 29% to 25% 
  • approximately 75% increase in offtake charges in Q1 2022 vs Q1-2021 (9% increase Q1-2022 vs Q4-2021) largely related to rollback, treatment, and escalator charges.

The graphics below illustrate changes in costs, treatment charges, and credits between Q1-2021 and Q1-2022.

Chart 1

Chart 2

About Altaley Mining Corporation

Altaley Mining Corporation is a Canadian based mining company with two 100% owned Mexican gold, silver, and base metal mining projects.

Altaley’s Tahuehueto mining project is in north-western Durango State, Mexico where construction has been advanced to near completion on its 1,000 tonne per day processing facility and related mine infrastructure for production of gold, silver, lead, and zinc in concentrates at Tahuehueto. The Company began initial pre-production in May 2022 and ramping up to full production capacity late 2022.

Campo Morado is an operating polymetallic base metal mine with mining and milling equipment currently producing at an average of 2,200 tonnes per day and is currently estimated to be Mexico’s 6th largest zinc producer.

Visit: www.altaleymining.com

On Behalf of the Board of Directors

(signed) “Ralph Shearing”

Ralph Shearing, P. Geol,

CEO, President, and Director

Cautionary Note Regarding Production Decisions and Forward-Looking Statements

It should be noted that Altaley declared commercial production at Campo Morado and elected to initiate construction to go into production at Tahuehueto prior to completing full feasibility studies demonstrating economic and technical viability. Accordingly, readers should be cautioned that Altaley’s production decisions have been made without comprehensive feasibility studies of established reserves at Campo Morado and prefeasibility level reserves at Tahuehueto, such that there is greater risk and uncertainty as to future economic results from the Campo Morado mine and at Tahuehueto mine where reserves are established to the prefeasibility level of confidence and therefore a higher technical risk of failure than would be the case if full feasibility studies were completed and relied upon to make production decisions. Altaley has completed a preliminary economic assessment (“PEA”) mining study on the Campo Morado mine and a prefeasibility study (‘PFS”) at Tahuehueto mine that provides a conceptual life of mine plan and a preliminary economic analysis based on the previously identified mineral resources (see News Release dated November 8, 2017,  April 4, 2018, and April 25, 2022).

Statements contained in this news release that are not historical facts are “forward-looking information” or “forward-looking statements” (collectively, “Forward-Looking Information”) within the meaning of applicable Canadian securities laws. Forward-Looking Information includes but is not limited to conditions or financial performance that are based on assumptions about future economic conditions and courses of action; the timing and costs of future activities on the Company’s properties, such as production rates and increases; success of exploration, development and bulk sample processing activities, and timing for processing at its own mineral processing facility on the Tahuehueto project site. In certain cases, Forward-Looking Information can be identified using words and phrases such as “plans,” “expects,” “scheduled,” “estimates,” “forecasts,” “intends,” “anticipates” or variations of such words and phrases. In preparing the Forward-Looking Information in this news release, the Company has applied several material assumptions, including, but not limited to, that the current exploration, development, environmental and other objectives concerning the Campo Morado Mine and the Tahuehueto Project can be achieved: the continuity of the price of gold and other metals, economic and political conditions, and operations. Forward-Looking Information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance, or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the Forward-Looking Information. There can be no assurance that Forward-Looking Information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on Forward-Looking Information. Except as required by law, the Company does not assume any obligation to release publicly any revisions to Forward-Looking Information contained in this news release to reflect events or circumstances after the date hereof or to reflect the occurrence of unanticipated events.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

For further information about Altaley Mining Corporation, please contact:

Glen Sandwell
Corporate Communications Manager
ir@altaleymining.com
Tel: +1 (604) 684-8071

Altaley Mining Initiates Mining and Milling Operations at its New Tahuehueto Gold Mine in Durango, Mexico

Altaley Mining Corporation (TSXV: ATLY) (OTCQX: ATLYF) (FSE: TSGA) (“Altaley” or the “Company”) is excited to announce that the Company has initiated pre-production mining and mill commissioning operations at its Tahuehueto Gold Mine in Durango, Mexico. Construction efforts at the mine site have advanced to allow the startup and commission of one ball mill capable of processing up to 500 tpd.

“I am very excited to see Tahuehueto commencing pre-production activities and look forward with anticipation to our first concentrate deliveries, anticipated in several weeks, which will bring our Company its first revenue from the new, on-site Tahuehueto mineral processing facility” states Ralph Shearing, CEO, “The Tahuehueto gold mine coming on-line is the realization and delivery to shareholders of the Company’s major goal of reaching production on its flagship asset. The robust cash flows anticipated from Tahuehueto should allow us to accelerate our debt repayments; our cash flow modeling suggests all loan debt may be repaid in under two years.  We will also re-initiate exploration activities to expand reserves and resources, which exploration I am convinced, can unlock the hidden, undiscovered ultimate potential of this district-scale project allowing mine expansion and extension to the current life of mine.”  Listen to Ralph’s interview with Proactive Investors as he describes the milestone event at Tahuehueto.

Tahuehueto’s processing facility is operational allowing for milling up to 500tpd with flotation cells, concentrate thickeners and concentrate filters successfully tested and operational.

During the commissioning phase of the first ball mill, a bulk concentrate will be produced and as soon as possible thereafter, the Company will process a separate precious metal rich lead concentrate and a zinc concentrate. Copper concentrate production is planned to be initiated late 2022.

Electrical power generation is being supplied by Aggreko International Power Projects Limited who have installed power generation equipment capable of supplying power to the mining unit for 1,000 tpd sustained production. The water pumping system and pipeline is operational to supply processing water to the mine at its full planned capacity of 1,000 tpd.

The Company has stockpiled over 29,000 tonnes of ore to be used in the commissioning process and pre-production phases of the 1st ball mill.  As soon as the process plant completes its start-up commissioning phase and has been optimized for maximum recoveries and throughput, higher grade run of mine ore will begin to be processed to maximize revenues during the pre-production phases of the mine. 

Altaley’s underground mining contractor has developed access to four stopes, two on the El Creston structure and two on the Perdido structure, providing multiple working faces more than fully capable to supply adequate mill feed for the mine’s start-up 500 tpd phase.   Underground development is continuing and will soon provide access to 2 additional stopes on Perdido and four additional stopes on El Creston at lower elevations and thereby will have completed access at least 10 mining stopes capable of supplying mill feed to the 1,000 tpd operation upon completion of construction as described below.

Remaining construction to advance the mine to its planned full production capacity of 1,000 tpd is as follows:

2nd Ball Mill installation

Installation of the second 500 tpd ball mill to increase milling capacity to 1000 tpd is planned to be completed in Q3, 2022. Necessary equipment has been acquired, the majority of which is stored on site or in the Company’s Durango warehouse.

Crushing Circuit

Initial crushing is being handled with a temporary crusher, fully capable of continually feeding the 500 tpd ball mill, while the Company completes construction of the mine’s permanent crushing circuit, which will contain a primary jaw crusher and secondary cone crusher with associated vibrating screens and storage hoppers. All crushing equipment is on site or in the Company’s Durango warehouse ready for installation. The permanent crushing circuit is approximately 50% complete and expected  to be completed during June 2022.

Tailings Thickener and Dewatering

The tailings thickener is functional and tailings filter presses for dewatering are scheduled for installation over the next several weeks to be operational during June 2022.  Temporary tailings storage is available to accept pre-production tailings until the formal dry stack tailings storage facility is ready to accept dewatered tailings, which is expected by the end of August 2022.

About Altaley Mining Corporation

Altaley Mining Corporation is a Canadian based mining company with two 100% owned Mexican gold, silver, and base metal mining projects.

Altaley’s Tahuehueto mining project is in north-western Durango State, Mexico where construction has been advanced to near completion on its 1,000 tonne per day processing facility and related mine infrastructure to initiate production of gold, silver, lead, and zinc in concentrates at Tahuehueto. The Company is targeting initial pre-production in May 2022 and ramping up to full production capacity during Q3 2022.

Campo Morado is an operating polymetallic base metal mine with mining and milling equipment currently producing at an average of 2,200 tonnes per day and is currently estimated to be Mexico’s 6th largest zinc producer.

Visit: www.altaleymining.com

On Behalf of the Board of Directors

(signed) “Ralph Shearing”

Ralph Shearing, P. Geol,

CEO, President, and Director

Cautionary Note Regarding Production Decisions and Forward-Looking Statements

It should be noted that Altaley declared commercial production at Campo Morado and elected to initiate construction to go into production at Tahuehueto prior to completing full feasibility studies demonstrating economic and technical viability. Accordingly, readers should be cautioned that Altaley’s production decisions have been made without comprehensive feasibility studies of established reserves at Campo Morado and prefeasibility level reserves at Tahuehueto, such that there is greater risk and uncertainty as to future economic results from the Campo Morado mine and at Tahuehueto mine where reserves are established to the prefeasibility level of confidence and therefore a higher technical risk of failure than would be the case if full feasibility studies were completed and relied upon to make production decisions. Altaley has completed a preliminary economic assessment (“PEA”) mining study on the Campo Morado mine and a prefeasibility study (‘PFS”) at Tahuehueto mine that provides a conceptual life of mine plan and a preliminary economic analysis based on the previously identified mineral resources (see News Release dated November 8, 2017,  April 4, 2018, and April 25, 2022).

Statements contained in this news release that are not historical facts are “forward-looking information” or “forward-looking statements” (collectively, “Forward-Looking Information”) within the meaning of applicable Canadian securities laws. Forward-Looking Information includes but is not limited to conditions or financial performance that are based on assumptions about future economic conditions and courses of action; the timing and costs of future activities on the Company’s properties, such as production rates and increases; success of exploration, development and bulk sample processing activities, and timing for processing at its own mineral processing facility on the Tahuehueto project site. In certain cases, Forward-Looking Information can be identified using words and phrases such as “plans,” “expects,” “scheduled,” “estimates,” “forecasts,” “intends,” “anticipates” or variations of such words and phrases. In preparing the Forward-Looking Information in this news release, the Company has applied several material assumptions, including, but not limited to, that the current exploration, development, environmental and other objectives concerning the Campo Morado Mine and the Tahuehueto Project can be achieved: the continuity of the price of gold and other metals, economic and political conditions, and operations. Forward-Looking Information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance, or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the Forward-Looking Information. There can be no assurance that Forward-Looking Information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on Forward-Looking Information. Except as required by law, the Company does not assume any obligation to release publicly any revisions to Forward-Looking Information contained in this news release to reflect events or circumstances after the date hereof or to reflect the occurrence of unanticipated events.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

For further information about Altaley Mining Corporation, please contact:

Glen Sandwell
Corporate Communications Manager
ir@altaleymining.com
 Tel: +1 (604) 684-8071

Altaley Mining Discloses 2021 Financial and Operating Results, Reporting Net Income of $36.2 Million and $0.15 earnings per share

Altaley Mining Corporation (TSXV: ATLY) (OTCQX: ATLYF) (FSE: TSGA) (“Altaley” or the “Company”) is pleased to announce the SEDAR filing of its audited consolidated financial statements and management discussion & analysis for the year ended December 31, 2021. 

2021 Financial Highlights
  • 121% increase in gross revenues to $98.4M
  • Mine operating profit increased to $34.2M from a 2020 loss of $138K
  • Basic earnings per share of $0.15
  • Positive net income of $36.2M, up from the previous year’s loss of $11.6M

Ralph Shearing, CEO states,” I am immensely proud of our entire Altaley team who have worked tirelessly throughout 2021 to deliver a record-breaking year of rapid growth and excellent profitability to the Company and our shareholders. We will build on these excellent 2021 results as we continue our improvements at Campo Morado and very soon, enter production at our Tahuehueto gold mine where we expect robust economics to significantly increase our revenues and profitability.”  Please see recent press release dated April 26, 2022, disclosing Tahuehueto pre-feasibility results.

Highlights of Campo Morado Mine
  • 2021 average   AISC of $0.83/lb Zn. and C1 cash cost per lbs of US$0.60
  • Produced 45,778 tonnes of zinc concentrate grading an average of 46% zinc, 2.12 g/t gold, 658 g/t silver and sold approximately 45,680 tonnes of zinc concentrate generating 2021 revenue of US$52.14M
  • Produced 9,936 tonnes of lead concentrate grading an average of 22% lead, 1.65% copper, 6.08 g/t gold, 776 g/t silver and sold 9,657 tonnes generating 2021 revenue of US$8.96M.
  • Mined 689,963 tonnes of ore grading 4.27% zinc, 1.09% lead, 124 g/t silver and 1.06 g/t gold.
  • An estimated 689,963 tonnes of mineralized material were processed during year ended December 31, 2021,

The following table provided a summary of the operating performance of the Company for the three months and years ended December 31, 2021, and 2020. (Dollar amounts expressed in thousands of Canadian dollars, unless otherwise stated).

Campo Morado Mine Q4 operating income for the three months and year ended December 31, 2021, and 2020, is comprised of:

Private Placement

The TSXV has provided the Company with a thirty-day extension to close the 2nd and final tranche of the private placement first announced on March 17, 2022.

About Altaley Mining Corporation

Altaley Mining Corporation is a Canadian based mining company with two 100% owned Mexican gold, silver, and base metal mining projects.

Altaley’s Tahuehueto mining project is in north-western Durango State, Mexico where construction has been advanced to near completion on its 1,000 tonne per day processing facility and related mine infrastructure to initiate production of gold, silver, lead, and zinc in concentrates at Tahuehueto. The Company is targeting initial pre-production in May 2022 and ramping up to full production capacity during Q2-Q3 2022.

Campo Morado is an operating polymetallic base metal mine with mining and milling equipment currently producing at an average of 2,200 tonnes per day and is currently estimated to be Mexico’s 6th largest zinc producer.

Visit: www.altaleymining.com

On Behalf of the Board of Directors

(signed) “Ralph Shearing”

Ralph Shearing, P. Geol,

CEO, President, and Director

Cautionary Note Regarding Production Decisions and Forward-Looking Statements

It should be noted that Altaley declared commercial production at Campo Morado and elected to initiate construction to go into production at Tahuehueto prior to completing full feasibility studies demonstrating economic and technical viability. Accordingly, readers should be cautioned that Altaley’s production decisions have been made without comprehensive feasibility studies of established reserves at Campo Morado and prefeasibility level reserves at Tahuehueto, such that there is greater risk and uncertainty as to future economic results from the Campo Morado mine and at Tahuehueto mine where reserves are established to the prefeasibility level of confidence and therefore a higher technical risk of failure than would be the case if full feasibility studies were completed and relied upon to make production decisions. Altaley has completed a preliminary economic assessment (“PEA”) mining study on the Campo Morado mine and a prefeasibility study (‘PFS”) at Tahuehueto mine that provides a conceptual life of mine plan and a preliminary economic analysis based on the previously identified mineral resources (see News Release dated November 8, 2017,  April 4, 2018, and April 25, 2022).

Statements contained in this news release that are not historical facts are “forward-looking information” or “forward-looking statements” (collectively, “Forward-Looking Information”) within the meaning of applicable Canadian securities laws. Forward-Looking Information includes but is not limited to conditions or financial performance that are based on assumptions about future economic conditions and courses of action; the timing and costs of future activities on the Company’s properties, such as production rates and increases; success of exploration, development and bulk sample processing activities, and timing for processing at its own mineral processing facility on the Tahuehueto project site. In certain cases, Forward-Looking Information can be identified using words and phrases such as “plans,” “expects,” “scheduled,” “estimates,” “forecasts,” “intends,” “anticipates” or variations of such words and phrases. In preparing the Forward-Looking Information in this news release, the Company has applied several material assumptions, including, but not limited to, that the current exploration, development, environmental and other objectives concerning the Campo Morado Mine and the Tahuehueto Project can be achieved: the continuity of the price of gold and other metals, economic and political conditions, and operations. Forward-Looking Information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance, or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the Forward-Looking Information. There can be no assurance that Forward-Looking Information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on Forward-Looking Information. Except as required by law, the Company does not assume any obligation to release publicly any revisions to Forward-Looking Information contained in this news release to reflect events or circumstances after the date hereof or to reflect the occurrence of unanticipated events.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

For further information about Altaley Mining Corporation, please contact:

Glen Sandwell
Corporate Communications Manager
ir@altaleymining.com
 Tel: +1 (604) 684-8071